For reasons unclear, the City Council has moved their worksession away from Council Chambers (and the CCTV cameras) so you'll have to come out to the Anderson Room at the Salem Public Library this Wednesday, 11/28, at 5:30 p.m. to see whether the City Council intends to do its job and subject the most expensive public project proposal in Salem's history to the kind of serious, skeptical scrutiny that it deserves, or whether they just hope to let the Concrete Lobby roll by them.
Remember, this is a council that devoted HOURS and HOURS to public meetings and multiple public hearings to whether Salem residents could keep a few chickens in the yard. This is a decision with a million times more magnitude, so this merits at least dozens of times the level of investigation.
Here's a scorecard for you for Wednesday night, so you can see which council members take their responsibilities seriously (by demanding serious, research-based answers on each issue):
How many of these
critical issues does the Salem City Council address at its November 28th work
session on the Third Bridge?
c The
Council discusses a plan to pay for the 3rd Bridge, acknowledging that it will
involve considerable local revenue from tolls on all bridges, a property tax
ballot measure, or a gas tax increase.
c The
Council discusses the fact that traffic on the existing bridges is at a 10-year
low and that this trend is likely to continue with increasing gas prices and
other changes in people's driving habits.
c The
Council discusses the fact that the 3rd Bridge will require purchasing 75 acres
of new right-of-way that will displace over 160 homes and businesses.
c The
Council discusses the fact that the 3rd bridge will create visual and noise
pollution through neighborhoods for 2.7 miles from West Salem to Highland when
these residents find themselves under the longest elevated freeway in Oregon.
c The
Council discusses the fact that the 3rd Bridge will reduce the size of Wallace
Marine Park and destroy the beauty and natural setting of much of the park.
c The
Council discusses the fact that planning for the 3rd Bridge is $5.5 million
over its original $2 million planning budget and is four years late.
c The
Council discusses the fact that a financing package was promised in August of
2008 and that it is highly unusual to wait until a design is approved before
deciding how to fund it.
c The
Council discusses the fact that after six years of meetings, the preliminary
preferred alternative (4D) for the 3rd Bridge did not receive support from a
majority of the Salem River Crossing Planning Task Force.
c The
Council discusses the fact that all three of the Neighborhood Associations that
are in the path of the 3rd Bridge are on record as opposing it.
c The
Council discusses the fact that the 3rd Bridge will take retail business away
from Salem by making it easier to get to Keizer Station and the Woodburn Outlet
Mall.
c The
Council discusses the fact that plans for the 3rd Bridge plan ignore less
expensive options to relieve peak hour congestion, such as off-ramps to fix the
ends of the existing bridges with better traffic flow to Glen Creek Drive and
Front Street north, and bike lanes and better transit to West Salem.